Original Detailed estimate sanctioned for Rs.374.15 Cr by Railway Board in November 2015.

Bye - pass at Vijayawada (Revised alignment – 26.00 KM): 
Review of work has been done by Operating department and alignment has been changed  with two Rail Over Rail (ROR) from Mustabada to Rayanapadu.  

Modified revised estimate for Proposed Bye-pass line with Rail - Over - Rail (ROR) flyovers at ends between Mustabada & Rayanapadu Stations (bye-passing Vijayawada Junction) connecting BZA-VSKP line & BZA-KZJ line for a value   of CRs.497.60 sanctioned by Railway Board.

Land acquisition requisitions submitted to District Collector/Krishna to an extent of  38.414 Acres submitted and joint measurements completed.

Preparation of tender schedule for yards is in progress.