Original Detailed estimate sanctioned for Rs.374.15 Cr by Railway Board in November 2015.
Bye - pass at Vijayawada (Revised alignment – 26.00 KM):
Review of work has been done by Operating department and alignment has been changed with two Rail Over Rail (ROR) from Mustabada to Rayanapadu.
Modified revised estimate for Proposed Bye-pass line with Rail - Over - Rail (ROR) flyovers at ends between Mustabada & Rayanapadu Stations (bye-passing Vijayawada Junction) connecting BZA-VSKP line & BZA-KZJ line for a value of CRs.497.60 sanctioned by Railway Board.
Land acquisition requisitions submitted to District Collector/Krishna to an extent of 38.414 Acres submitted and joint measurements completed.
Preparation of tender schedule for yards is in progress.