Sunday, December 1, 2019

December 01, 2019

Bitragunta Turntable


An archival photo of a turntable used for reversing of steam engines at Bitragunta Loco Shed in Andhra Pradesh.

Inaugurated in:1934 (loco round house in 1908 and shed in 1934)
Turntable was used for reversing of steam engines (Change the direction) at one of the biggest junction in Southern India, at that time.

During it's heyday, 2500 employees used to work in this shed to repair steam engines..
The shed was active till the arrival of Electric locomotives(1982) and was dismantled in 2011.

Anecdote: Bitragunta was an important landmark for railways and it was one of the biggest locomotive sheds in Indian railways till steam engines were replaced by diesel and electrical locomotives. The loco shed was constructed in 1885 and the roundhouse with turntable facility was added in 1934.The shed had capacity to handle 50 steam locomotives with major yard and an inter-changing depot for drivers and guards. It is still an inter-changing depot for guards and drivers manning goods and passenger trains.


December 01, 2019

Construction of New Bridge – Proposed Improvements to Nallamada Drain



Proposed improvements to Nallamada drain – Construction of new bridge No.617 as 6 x 18.30 m PSC girders for both Up  & Dn lines between Bapatla & Appikatla stations

Status: 
Revised estimate sanctioned for a value of Rs.25.79 Crores

Work completed in all respects except cut and connection works

CRS sanction obtained

Tender finalised and work awarded to the agency. Agency commenced the work.

Block works will be taken up in December 2019.

December 01, 2019

Bye-pass (ROR) at VIJAYAWADA


Original Detailed estimate sanctioned for Rs.374.15 Cr by Railway Board in November 2015.

Bye - pass at Vijayawada (Revised alignment – 26.00 KM): 
Review of work has been done by Operating department and alignment has been changed  with two Rail Over Rail (ROR) from Mustabada to Rayanapadu.  

Modified revised estimate for Proposed Bye-pass line with Rail - Over - Rail (ROR) flyovers at ends between Mustabada & Rayanapadu Stations (bye-passing Vijayawada Junction) connecting BZA-VSKP line & BZA-KZJ line for a value   of CRs.497.60 sanctioned by Railway Board.

Land acquisition requisitions submitted to District Collector/Krishna to an extent of  38.414 Acres submitted and joint measurements completed.

Preparation of tender schedule for yards is in progress.

December 01, 2019

Machilipatnam (C&W Depot) – Augmentation of Coach Maintenance Facilities



Year of Sanction : 2011-12
Last Sanctioned Cost : Rs.10.76 Cr
BG 2019-20 : Rs.9.30 Cr
Expenditure Upto November 2019 : Rs.2.235 Cr

Status of estimate: Sanctioned by GM/SC
Status of GAD:  Approved.
Status of Work: 
Pit Line:  2 nd Pit line work completed and commissioned in March’2018
IOH Shed : Tenders finalized and LOA issued to the Agency. Structural steel procured for shed and fabrication work is in progress.

December 01, 2019

Narasapur (C&W Deport) - 24 Coach length Pitline as per CAMTECH Design


Year of Sanction : 2011-12

Last Sanctioned Cost : 9.59 Cr

BG 2019-20 : 15 Cr

Expenditure upto November 2019 : 12.225 Cr

Status of estimate: Sanctioned by GM

Status of ESP:  Approved.  SIP  approved.

Status of Work:  
Stabling Lines: NI work completed in March’2019 and new stabling lines commissioned for traffic.

Pit Line:  Out of 16 coach Pit line construction of Pit line for 6 coaches completed and further work is in progress. 


December 01, 2019

Augmentation of Homing Capacity of Electric Loco Shed, Vijayawada from 175 to 225


Year of Sanction: 2012-13
Last Sanctioned Cost: 24.33 
Expenditure upto March 2019 : 0.43
BG 2019-20 : 13.467
Expenditure in 2019-20 : 11.589

Status of Estimate: Sanctioned by GM

Status of GAD:  Approved

Status of Work:  Works completed : Construction of Grease Godown. Renovation of tool room completed.

Works in Progress :
H/L bay:  Flooring 50 % completed. Balance in progress. TDC : Feb’2020

Extension of Inspection bay:  Foundations completed. Columns & trusses erected.

Pit line works completed and flooring works are in progress. TDC : Jan 2020

Extension of L/L bay:  Foundations completed and fabrication of structural steel, erection and Sheeting works completed.

Extension of pit line works to be taken up TDC : Feb 2020

Ladies rest room is in progress TDC : Feb 2020. 

Tenders finalized and LOA issued to the Agency. Stores building is in progress.
TDC- September - 2020.
December 01, 2019

Rayanapadu - Modernisation of Wagon Workshop


Year of Sanction: 2009 – 10

Revised Estimate sanctioned for Rs 98.94 Cr

Status of GAD:   Approved

Estimate
Revised estimate for Rs 98.94 Cr is sanctioned by CAO/C/SC.

Status of Work

Completed: Re-roofing of Exg. Sheds (All 12 spans Re-roofing). New ‘B’ Sub station building, Energy monitoring cell, ‘E’ sub-station building & SSEs office Completed.

Addl bay for Body Repair shop &  Addl. Bay for Bogie repair shop,  C Sub station, Ladies waiting hall. 

Extension of Paint shop & Covered shed for materials, NTXR building.

Replacement of Open gantry with new structures  completed. 

New works : Tenders finalized and LOA issued. Construction of UT lab, ladies waiting hall, First Aid center, Stripping shop, Gas Godown are in progress.

TDC : Dec’ 2020



December 01, 2019

Gudur Junction - Additional Platform between Road No. 4 to 5



Status of GAD: 
Revised Yard plan ESP approved on April,  2018
SIP approved.

Status of Work: 

NI works completed. Construction of platform No.4 and 5 completed and commissioned for passenger traffic on 17-07-2019/01-09-2019 respectively
Cover over platform for 3 spans is to be taken up – TDC : January 2020
Provision of landing to the existing FOB on North Side for PF 4&5. – TDC : January 2020
Construction of goods platform for a length of 190 m to be done – TDC : March 2020

December 01, 2019

Regupalem, Elamanchali & Narsingapalli - Extension of Loop Lines

Regupalem, Elamanchali & Narsingapalli - Extension of Loop Lines





Regupalem: Commissioned on 07.05.2012

Elamanchili: Commissioned on 16.09.2015

Narasingapalli: Revised Estimate for Rs. 25.80 Cr sanctioned by  Railway Board on 23.08.2018.
Work awarded for construction of Station building with RBG rooms and work commenced.
Funds Allotted : Rs.2.00 Cr
Tenders for track linking works under preparation
TDC : March’ 2020


December 01, 2019

Vijayawada - Modification to Bulb and CR Goods Lines


Year of sanction: 2012-13

Status of the Work
  • Detailed estimate sanctioned for Rs.26.45 Cr on 29.11.13
  • 2.10 acres of land acquired in March 2018
Status of GAD
  • ESP approved in 2013. Major alteration with Sand humps also approved in Aug 18.
  • SIP approved. Work involves  4 cabins. S&T Cables 180 KM required.
Current Status
  • Engineering: Building 1st floor (RBG rooms) completed. Minor bridges 4 out of 4 completed. Balance earth work about 18000 Cum is in progress. 
  • Acquisition of 0.445 Acres of land has been taken over from Revenue Authorities on 30-11-2019.
  • S&T:  Tender awarded and works are in progress.
  • OHE:  Tenders finalized.
  • BG Outlay: Rs 4.0 Cr, Spent Rs 4.0 Cr.  Fund required Rs 13.0 Cr (projected in RE).  Additional funds : Rs. 6.00 Cr. Allotted.
  • TDC: January 2020 