Narasapur (C&W Deport) - 24 Coach length Pitline as per CAMTECH Design


Year of Sanction : 2011-12

Last Sanctioned Cost : 9.59 Cr

BG 2019-20 : 15 Cr

Expenditure upto November 2019 : 12.225 Cr

Status of estimate: Sanctioned by GM

Status of ESP:  Approved.  SIP  approved.

Status of Work:  
Stabling Lines: NI work completed in March’2019 and new stabling lines commissioned for traffic.

Pit Line:  Out of 16 coach Pit line construction of Pit line for 6 coaches completed and further work is in progress. 