Narasapur (C&W Deport) - 24 Coach length Pitline as per CAMTECH Design
Year of Sanction : 2011-12
Last Sanctioned Cost : 9.59 Cr
BG 2019-20 : 15 Cr
Expenditure upto November 2019 : 12.225 Cr
Status of estimate: Sanctioned by GM
Status of ESP: Approved. SIP approved.
Status of Work:
Stabling Lines: NI work completed in March’2019 and new stabling lines commissioned for traffic.
Pit Line: Out of 16 coach Pit line construction of Pit line for 6 coaches completed and further work is in progress.