Machilipatnam (C&W Depot) – Augmentation of Coach Maintenance Facilities
Year of Sanction : 2011-12
Last Sanctioned Cost : Rs.10.76 Cr
BG 2019-20 : Rs.9.30 Cr
Expenditure Upto November 2019 : Rs.2.235 Cr
Status of estimate: Sanctioned by GM/SC
Status of GAD: Approved.
Status of Work:
Pit Line: 2 nd Pit line work completed and commissioned in March’2018
IOH Shed : Tenders finalized and LOA issued to the Agency. Structural steel procured for shed and fabrication work is in progress.