Sunday, December 1, 2019

Vijayawada - Modification to Bulb and CR Goods Lines


Year of sanction: 2012-13

Status of the Work
  • Detailed estimate sanctioned for Rs.26.45 Cr on 29.11.13
  • 2.10 acres of land acquired in March 2018
Status of GAD
  • ESP approved in 2013. Major alteration with Sand humps also approved in Aug 18.
  • SIP approved. Work involves  4 cabins. S&T Cables 180 KM required.
Current Status
  • Engineering: Building 1st floor (RBG rooms) completed. Minor bridges 4 out of 4 completed. Balance earth work about 18000 Cum is in progress. 
  • Acquisition of 0.445 Acres of land has been taken over from Revenue Authorities on 30-11-2019.
  • S&T:  Tender awarded and works are in progress.
  • OHE:  Tenders finalized.
  • BG Outlay: Rs 4.0 Cr, Spent Rs 4.0 Cr.  Fund required Rs 13.0 Cr (projected in RE).  Additional funds : Rs. 6.00 Cr. Allotted.
  • TDC: January 2020 