Vijayawada - Modification to Bulb and CR Goods Lines
Year of sanction: 2012-13
Status of the Work
- Detailed estimate sanctioned for Rs.26.45 Cr on 29.11.13
- 2.10 acres of land acquired in March 2018
Status of GAD
- ESP approved in 2013. Major alteration with Sand humps also approved in Aug 18.
- SIP approved. Work involves 4 cabins. S&T Cables 180 KM required.
Current Status
- Engineering: Building 1st floor (RBG rooms) completed. Minor bridges 4 out of 4 completed. Balance earth work about 18000 Cum is in progress.
- Acquisition of 0.445 Acres of land has been taken over from Revenue Authorities on 30-11-2019.
- S&T: Tender awarded and works are in progress.
- OHE: Tenders finalized.
- BG Outlay: Rs 4.0 Cr, Spent Rs 4.0 Cr. Fund required Rs 13.0 Cr (projected in RE). Additional funds : Rs. 6.00 Cr. Allotted.
- TDC: January 2020