Sunday, December 1, 2019

Augmentation of Homing Capacity of Electric Loco Shed, Vijayawada from 175 to 225


Year of Sanction: 2012-13
Last Sanctioned Cost: 24.33 
Expenditure upto March 2019 : 0.43
BG 2019-20 : 13.467
Expenditure in 2019-20 : 11.589

Status of Estimate: Sanctioned by GM

Status of GAD:  Approved

Status of Work:  Works completed : Construction of Grease Godown. Renovation of tool room completed.

Works in Progress :
H/L bay:  Flooring 50 % completed. Balance in progress. TDC : Feb’2020

Extension of Inspection bay:  Foundations completed. Columns & trusses erected.

Pit line works completed and flooring works are in progress. TDC : Jan 2020

Extension of L/L bay:  Foundations completed and fabrication of structural steel, erection and Sheeting works completed.

Extension of pit line works to be taken up TDC : Feb 2020

Ladies rest room is in progress TDC : Feb 2020. 

Tenders finalized and LOA issued to the Agency. Stores building is in progress.
TDC- September - 2020.