Rayanapadu - Modernisation of Wagon Workshop
Year of Sanction: 2009 – 10
Revised Estimate sanctioned for Rs 98.94 Cr
Status of GAD: Approved
Estimate
Revised estimate for Rs 98.94 Cr is sanctioned by CAO/C/SC.
Status of Work
Completed: Re-roofing of Exg. Sheds (All 12 spans Re-roofing). New ‘B’ Sub station building, Energy monitoring cell, ‘E’ sub-station building & SSEs office Completed.
Addl bay for Body Repair shop & Addl. Bay for Bogie repair shop, C Sub station, Ladies waiting hall.
Extension of Paint shop & Covered shed for materials, NTXR building.
Replacement of Open gantry with new structures completed.
New works : Tenders finalized and LOA issued. Construction of UT lab, ladies waiting hall, First Aid center, Stripping shop, Gas Godown are in progress.
TDC : Dec’ 2020