Sunday, December 1, 2019

Rayanapadu - Modernisation of Wagon Workshop


Year of Sanction: 2009 – 10

Revised Estimate sanctioned for Rs 98.94 Cr

Status of GAD:   Approved

Estimate
Revised estimate for Rs 98.94 Cr is sanctioned by CAO/C/SC.

Status of Work

Completed: Re-roofing of Exg. Sheds (All 12 spans Re-roofing). New ‘B’ Sub station building, Energy monitoring cell, ‘E’ sub-station building & SSEs office Completed.

Addl bay for Body Repair shop &  Addl. Bay for Bogie repair shop,  C Sub station, Ladies waiting hall. 

Extension of Paint shop & Covered shed for materials, NTXR building.

Replacement of Open gantry with new structures  completed. 

New works : Tenders finalized and LOA issued. Construction of UT lab, ladies waiting hall, First Aid center, Stripping shop, Gas Godown are in progress.

TDC : Dec’ 2020