Gudur Junction - Additional Platform between Road No. 4 to 5
Status of GAD:
Revised Yard plan ESP approved on April, 2018
SIP approved.
Status of Work:
NI works completed. Construction of platform No.4 and 5 completed and commissioned for passenger traffic on 17-07-2019/01-09-2019 respectively
Cover over platform for 3 spans is to be taken up – TDC : January 2020
Provision of landing to the existing FOB on North Side for PF 4&5. – TDC : January 2020
Construction of goods platform for a length of 190 m to be done – TDC : March 2020